On 8/8/2013 6:33 AM, Lucian Ciufudean wrote:
I might have not been clear.
Let's say I start a chef run with 1k recipes and it will take 24h to execute, is there a callback mechanism that chef uses while the run is in progress, not after its completion as is the case with report handlers? I want to be able to say to the user at one moment that "55 out of 1000 resources executed".

I'm not aware of such a thing built into Chef, but one has to wonder what the real value of that is if step 56 is going to take 2hrs, 57-83 will take 45 seconds, 84 will take 20 minutes, etc.